FR

Events

Discover Visual planning 10

Contact

Have a question or project?
Our team is here to help.

Customer Stories & Case Studies

See how organizations improve scheduling, streamline operations, and gain better visibility across teams and workloads.

SNCF

Manage 12,000 employees with real time scheduling

Airbus

Centralize field operations across teams and sites

User Community

Connect, share and learn with the Visual Planning community

Exclusive Events

Webinars, workshops and community sessions

Knowledge Sharing

Best practices and operational feedback

Early Access

Preview upcoming features and product updates

Methodology

What is the critical path?

The critical path is the sequence of tasks in a project where any delay directly pushes back the project's overall finish date, because there's no slack time between them.

Visual Planning gestion de projets

How do you calculate the critical path?

It's calculated by mapping every task's dependencies and duration, typically from a Gantt chart or a PERT network. Tasks not on the critical path have slack (or "float") — meaning they can slip without affecting the overall finish date.

Why does the critical path matter?

It lets a project manager focus attention on the tasks that actually determine whether the deadline is met, instead of tracking every single task with equal urgency.

Real-world example

On a building project, pouring the foundation has to finish before framing can start — both tasks sit on the critical path. Landscaping, which can happen anytime before handoff, has slack and isn't critical.

What are the pros and cons of tracking the critical path?

It helps managers focus oversight on the tasks that actually matter for the deadline. Its limit: calculating it by hand gets complicated fast on large projects, and it has to be recalculated any time a task's duration changes.

Key takeaways

  • The sequence of tasks with zero slack that sets the project's total duration.
  • Calculated from task dependencies and durations.
  • Can shift mid-project if a task runs late.

Visual Planning's Gantt chart automatically calculates and highlights the critical path on your projects.

Frequently asked questions

What is "float" or "slack" in a project?

It's the amount of time a task can slip without affecting the project's finish date. Tasks on the critical path have zero float.

Does the critical path change during a project?

Yes, it can shift to a different sequence of tasks as soon as a delay eats up the slack of a previously non-critical task.

Do I need software to calculate the critical path?

Not necessarily on a small project, but scheduling software like Visual Planning calculates it automatically once the number of tasks and dependencies grows.

Does the critical path only apply to construction?

No, it applies to any project with dependent tasks, across industries — IT, manufacturing, events, and more.

Related terms